oracle dbms_scheduler to run multiple procedures in parallel


I've trying to figure out oracle's DBMS_SCHEDULER (Oracle 11g) and need help setting up the following:

I have a procedure that calls a list of other procedures like this:

CREATE OR REPLACE
PROCEDURE RUN_JOBS AS
BEGIN
  MYUSER.MYPROCEDURE1();
  MYUSER.MYPROCEDURE2();
  MYUSER.MYPROCEDURE3();
  MYUSER.MYPROCEDURE4();
  MYUSER.MYPROCEDURE5();
END;
/

I would like to use DBMS_SCHEDULER to run MYPROCEDURE3(), MYPROCEDURE4(), MYPROCEDURE5() in parallel after the completion of MYPROCEDURE2().

Can someone show me an example on how to set this up?


Solution

  • You can refer to Chains under the DBMS_SCHEDULER package: http://docs.oracle.com/cd/B28359_01/server.111/b28310/scheduse009.htm

    You can also achieve the same by going through Oracle Enterprise Manager, but I can't find any links to documentation right now.