How do I include end-to-end tests across microservices into multiple continuous delivery pipelines?


My team develops three microservices. The three work together to provide a business scenario. They communicate with REST and RabbitMQ. Looks like in Toby Clemson's presentation on Microservice Testing.

Each microservice has its own continuous delivery pipeline. They are delivery, not deployment pipelines, meaning there is a manual release decision at the end.

How do I include an end-to-end test for the business scenario, i.e. across all microservices, into the delivery pipelines?

My team suggested this:

We add one shared end-to-end stage that deploys all three microservices and runs the end-to-end test on them. Each time one of the pipelines reaches this stage, it deploys and tests. A semaphore ensures the pipelines pass the stage one after the other. Failure stops all three pipelines.

Shared end-to-end stage

To me, this seems to sacrifice all the independence the microservice architecture wins in the first place:

So what's a better way to do this?


Solution

  • In short - Such an integration testing would not be part of the microservices development/deployement team and process, but a separate team having its own process. You can automate as much as possible in that team, but in the end you need a decision whether to release or not.

    The longer explanation:

    The Microservices architectural style was invented to help large organizations to manage large applications and avoiding overhead of communication and dependencies between teams. So if you want to follow this style, you should really have 3 independent teams - One for each service. Each of those teams would have complete responsibility over the whole life-cycle of their respective service. Now when you want to do end-to-end testing (often called integration testing) you would set up a 4th team that is responsible for those tests. And you would have one person being the responsible release manager who owns a staging/testing cluster and decides on when testing proves sufficiently to release a new version of a service into the wild. Your goal should be to decouple the teams as much as possible in terms of dependencies and release cycles of their services. If you want complete independence of the services teams you can also make the integration testing part of each team. Meaning you have testing/staging cluster for each team and a responsible testing/release manager role in each team.