The autosys job should trigger on the 40th day from the start of every quarter.
Scenario: 1 Jan 2021 + 40 days (inclusive start date) is on 9 Feb 2021
likewise, 10May2021 9Aug2021 9Nov2021
In case of the 40th day to be a non-working day (Sat and Sun), the job should be scheduled for the next business day.
Create an extended calendar as:
extended_calendar: QUARTER_START_40_PLUS
workday: mo,tu,we,th,fr
non_workday: W
holiday: W
holcal:
cyccal:
adjust: 39
condition: jan#1|apr#1|jul#1|oct#1
description: Runs on 40th day after start of quarter, incase its a sat or sun job runs on next mon
Next Run Dates:
09Aug2021
09Nov2021
09Feb2022
10May2022