Azure Boards - Display Configuration


We have our Azure Boards (Project associated with Agile Process) defined as Feature >Epic >Tasks >User Story.

In our Azure Boards (Boards >Board), it displays only the Epic and Feature. It does not display tasks Underneath and user stories unless we go inside the Individual Epic.

Only after we are inside the Feature/Epic it shows the Child Items associated with it.

I want to have complete hierarchy to be displayed on my Sprint view and Board view.

Any thoughts ?


Solution

  • The correct parent-child relationship of work items on Agile Process should be: Epic > Feature > User Story > Task.

    enter image description here

    If you do not follow this order when linking parent / child items, you may get some unexpected issues. Such as some items cannot display as normal.

    So, you need to change to the correct order.