I am trying to do a burndown graph on PowerBI.
My data is a list of tasks. Each task has a numerical value (EFFORT) assigned to it and there is a total amount of effort for any given month (sum of all EFFORT). As tasks as set to DONE, the ongoing effort should be deducted from a running total and that value used to plot a graph. I have 3 columns
I would like to have measure to calculate EFFORT REMAINING for each date, i.e.
EFFORT REMAINING = TOTAL EFFORT - (EFFORT WHEN TASKS ARE DONE FOR EACH DAY)
For example,
I did get the consecutive dates displaying:
Burndown = CALENDAR(DATE(2022,7,1),DATE(2022,7,31))
and also the total effort (starting value)
TOTAL EFFORT = SUM(Issues[EFFORT])
Now for each date in table, I need to minus the accumulating total of EFFORT when the status is set to DONE
EFFORT REMAINING = Burndown[TOTAL EFFORT]-SUM(Issues[EFFORT]="DONE" ....
Im stuck after this last point. Can anyone help, please?
you are so close to the answer ). Convert SUM(Issues[EFFORT]="DONE"
to:
CALCULATE(
SUM(Issues[EFFORT])
, SUM(Issues[Status]="DONE"
)
Have a nice day.