I am trying to understand the new scrum template of tfs2010. I understand that PBIs are implemented by SBTs. but how is an SBT linked to a sprint. I mean, how do I specify that this SBT belongs to this sprint.
Actually, there is a Product Backlog Item work item type.
You associate the two by setting the Iteration Path of the Sprint work item, then setting the same iteration path on the PBI (or any other work item).