Does evidence based scheduling work right with heterogenous estimations?


Observing one year of estimations during a project I found out some strange things that make me wonder if evidence based scheduling would work right here?

So, is it really a good idea to let the programmers break down the 30 hours task down to 4 or 2 hours steps during estimations? Won't this raise the standard deviation? (Ok, let them break it down - but perhaps after the estimations?!)