svnjirajira-agileatlassian-fisheye

Integrate Atlassian Jira with SVN


I use SCM Manager as SVN server for project in office. Recently, I decided to set up a issue tracker and project management, so I install Atlassian JIRA 7.1.4 and FishEye 3.8 .
To link each SVN commit with related issue, Jira can parse commit comment ( feature Smart Commit) and change the state of issues, but this feature doesn't work correctly and could not change the state of issue.

How can integrate SCM Manager with Jira ?

(Is there any other solution to link issues with commits?)


Solution

  • With the help of the Atlassian Team, we were able to find a solution:

    It appears that this functionality is available in SCM Manager. See support request for the developer to add it: How to change issue status using SCM JIRA.

    The developer Sebastian links to their SCM JIRA plugin page and notes the auto-close section.